Summary
The city awarded an $8.98 million contract to LGC Global to rehabilitate the 12-foot Colson-Palmer storm line, funded through the Sewer Fund — key stormwater infrastructure for the community.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
$8,975,351 paid from the Sewer Fund's capital project budget.
Residents who depend on the city's storm drainage system to prevent flooding.